Wednesday, November 18, 2015

State Route 29-Channelization-Updates Wk of Nov 22

State of California • Department of Transportation

CONSTRUCTION UPDATE

Date: November 18, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting Sunday, November 22

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
The following work is scheduled:

WEEK STARTING NOVEMBER 22, 2015
• Roadway widening excavation nb shoulder between Chaix Lane & Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane

Work scheduled 7:00 AM to 3:30 PM, Monday through Wednesday. No lane closures scheduled. Lanes may be shifted and widths may be reduced for safety. No night work scheduled. No work on Thursday, November 26 (Thanksgiving) or Friday, November 27.

WEEK STARTING NOVEMBER 29, 2015
• Roadway widening excavation northbound shoulder between Chaix Lane and Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane
• Asphalt widening paving between Stice Lane and Dowdell Lane
Work scheduled 7:00 AM to 3:30 PM, Monday through Friday. No lane closures scheduled.

Night Work
• Underground drainage pipe crossings and drainage inlets at the following locations: Sulphur Springs Avenue and Mill Lane within the Route 29 traveled way.

Work scheduled 7:00 PM to 6:00 AM, Monday through Friday. One-way traffic control will be used. Delays of up to 5 minutes expected.

See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #

No comments:

Post a Comment