Interstate 280 Bridge Hinge Replacement
Project
104-Hours (4 Days-8-Hours) Road Closure
Planned for Memorial Day Holiday Weekend
San Francisco – Construction has started for a bridge hinge replacement project
on Interstate 280 near Cesar Chavez Street.
During three extended-holiday weekends, the California Department of Transportation
will close I-280 in order to replace one bridge hinge on southbound I-280 and
three bridge hinges on northbound I-280.
The first closure is scheduled for the Memorial
Day weekend. Southbound I-280 will
be fully closed between downtown San Francisco and the Pennsylvania Avenue on-ramp.
Full southbound closure Begins: 9 p.m. Thursday evening, May 22
Full southbound closure Ends: 5 a.m., Tuesday morning, May 27.
Southbound on-ramp closures include:
- Mariposa
Street/18th Street on-ramp
- 6th
Street/Brannan on-ramp
- King
Street on-ramp
Detour: In general, southbound Interstate 280 traffic will detour to U.S.
101.
Note:
northbound I-280 will remain open over the Memorial Day Holiday Weekend.
Additional closures are planned for
- 4th
of July Holiday Weekend (Thursday, July 3 – Tuesday, July 8)
- Labor
Day Holiday Weekend (Thursday, August 28 – September 2)
For
more information about the project, visit the Department’s website at http://www.dot.ca.gov/dist4/projects/280Bridge,
or follow us on Twitter
@caltransd4.
###