Wednesday, May 28, 2014

Interstate 580 Scofield Avenue and Western Drive Bridge Decks Replacement Project Lane Closures Continue


Date:              May 27, 2014
District:         4 - Oakland
Contact:        Allyn Amsk
Phone:          (510) 286-5445        

FOR IMMEDIATE RELEASE

Interstate 580 Scofield Avenue and Western Drive
Bridge Decks Replacement Project
Lane Closures Continue


Contra Costa County – Lane closures resume tonight for the Interstate 580 construction project just east of the Richmond-San Rafael Bridge. The project is expected to be finished by mid-June. The contractor is currently completing final items and will have periodic night time closures. Lane closures will be as needed.

·         In general, until mid-June, Caltrans will close one westbound lane Monday night through Friday night, from 7 p.m. to 5 a.m.

·         In general, until mid-June, Caltrans will close one eastbound lane Monday night through Friday night, from 8 p.m. to 5 a.m.

·         Note: one eastbound lane at the Richmond-San Rafael bridge will be closed, Monday through Friday, from 8:30 p.m. to 4 a.m., to move scaffolding.  This work will continue until mid-June.

·         During these closures, motorists should expect travel delay and allow additional time to reach their destination.

This is an active construction site and the 45 MPH speed zone will be enforced by the California Highway Patrol. Drive cautiously through the construction zone and leave a safe traveling distance between your vehicle and the vehicle ahead of you and “Slow for the Cone Zone.”

For more information about the project, visit the Caltrans webpage at http://www.dot.ca.gov/dist4/580scofieldave/ 


# # #

No comments: