Friday, August 12, 2016

SR-29 Napa County-Overnight Paving Starts August 15

State of California • Department of Transportation

TRAFFIC ADVISORY

Date: August 12, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Overnight One-Way Traffic Controls
Start Monday, August 15

NAPA COUNTY – The California Department of Transportation (Caltrans) and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.

As part of the work, crews will start paving a section of SR-29 between Mee Lane and Charter Oak Drive on Monday, August 15 and be completed by Monday, August 22.

Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to pave SR-29 with overnight one-way traffic controls.

During one-way traffic controls, one lane of SR-29 will remain open at all times with crews alternating closures on northbound and southbound SR-29 to allow one-lane of traffic to proceed at a time.

To ensure public and worker safety, one-way traffic controls will be in effect on SR-29 between Mee Lane and Charter Oak Drive each night Monday through Saturday starting Monday, August 15 until Monday, August 22. Work starts at 7:00 PM each night and concludes at 6:00AM the following mornings.

Once the overall project is completed in early-mid September, motorists will benefit from new left-turn pocket lanes and new shoulders on SR-29.

For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/ Please be #BeWorkZoneAlert.

# # #

Monday, July 25, 2016

SR-29 Channelization Updates- Napa Co- wk of July 25

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: July 25, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting July 25, 2016

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the week-ahead project update for the week of July 25.

WEEK STARTING JULY 25, 2016-Daytime Work
• Sidewalk, curb and gutter work btwn Inglewood Av & El Bonita in southbound shoulder.
Work is 6:00AM to 6:00PM, Mon-Fri. No daytime lane closures scheduled. Shoulder closures are anticipated near Hall Winery. Intermittent one-way traffic flaggers will be present at Grayson Avenue during signal installation.

Night Work
• Hot mix asphalt paving starting btwn Mee Lane & Charter Oak Avenue, in both directions
Work is scheduled 7:00PM to 6:00AM, Monday night through Saturday morning. One-way traffic control, with a delay of up to 5 minutes will be in-place. Driveway access may be limited during these hours. Slow traffic is expected throughout the work zone due to heavy haul trucks.

• Miscellaneous operations throughout the project area including storm water control maintenance and concrete work.

For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/ Please be #BeWorkZoneAlert.

# # #

Tuesday, July 5, 2016

SR-29 Channelization Project Update wks July 5 & 11-Napa Co.

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: July 5, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting July 5, 2016

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.

Below is the week-ahead project update for the week of July 5 and July 11.

WEEK STARTING JULY 5, 2016-Daytime Work
• Roadway excavation and storm drain installation between Dowdell Lane and Charter Oak Avenue in the southbound shoulder
• Sidewalk and curb and gutter construction between Inglewood Avenue and Charter Oak Avenue in the southbound shoulder

Work is scheduled 6:00AM to 4:00PM, Mon-Fri. Work between Dowdell Lane and Charter Oak Avenue will occur behind concrete safety barriers. No lane closures scheduled. Slower traffic is anticipated due to the use of heavy equipment. No night work scheduled

WEEK STARTING JULY 10, 2016-Night Work
• Hot mix asphalt paving btwn Dowdell LN & Charter Oak AV in the southbound shoulder
• Temporary concrete barrier removal Dowdell LN & Charter Oak AV (Thur & Fri Nights)

Work is scheduled 7:00 PM to 6:00 AM, Monday evening through Saturday morning. Paving work will occur behind concrete safety barriers. Driveway access may be limited. One-way traffic with a delay of up to 5 minutes. Motorists should expect slow traffic. No day work scheduled.

For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/

Please be #BeWorkZoneAlert.
# # #

Wednesday, June 1, 2016

State Route 29-Channelization Project-Napa County wk June 1

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: June 1, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting June 1, 2016

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the week-ahead project update for the weeks of June 1, June 6 and June 12.

WEEK STARTING JUNE 1-JUNE 5
No work. Complete work stoppage for Wine Auction Week (June 1 through June 5).

WEEK STARTING JUNE 6, 2016
• Storm drain installation between Inglewood Ave and Lewelling Lane in the southbound shoulder
• Roadway excavation between Dowdell Lane and Charter Oak Ave in the southbound shoulder

Daytime work is scheduled 7:00 AM until 5:00 PM, Monday-Friday. Southbound shoulder work between Inglewood Avenue and Lewelling Lane and between Dowdell Lane and Charter Oak Avenue. No lane closures scheduled. Access to driveways and businesses will be maintained.

• Night concrete median shift btwn Dowdell Ln & Charter Oak closes sb shoulder for widening

Night work is 7:00 PM until 6:00 AM, Monday-Wednesday. One-way traffic control will be used. Delays of up to 5 minutes anticipated.

WEEK STARTING JUNE 12, 2016
• Roadway excavation btwn Dowdell Lane and Charter Oak Avenue in the southbound shoulder
Work is 7:00 AM to 5:00 PM, Monday-Friday. Work between Dowdell and Charter Oak Avenue will occur behind concrete barriers. No lane closures are scheduled. Slower traffic is anticipated due to use heavy equipment in the work zone. Full access to driveways and businesses will be maintained. No night work scheduled

For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/

Please be #BeWorkZoneAlert.
# # #

Thursday, May 19, 2016

SR29-Channezliaton Project-Napa Co Updates Starting May 22

State of California • Department of Transportation

CONSTRUCTION UPDATE

Date: May 18, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting Sunday, May 22

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the week-ahead project update for the week of May 22 and May 22.

WEEK STARTING MAY 22, 2016
Storm drain installation between Inglewood Avenue and Lewelling Lane in the southbound shoulder. Work will stop just south of Hall Winery.

Hours of work are 7:00 AM to 5:00 PM, Mon-Fri. Southbound shoulder work will occur behind portable delineators or traffic cones. No daytime lane closures are scheduled. Slower traffic is anticipated due to the ingress and egress of heavy equipment and off-haul trucks into and out of the work zone. Full access to driveways will be maintained.

Night Work
• Hot mix asphalt (HMA) paving between Dowdell Lane and Charter Oak Avenue in the northbound shoulder– Monday & Tuesday Nights
• Roadway re-striping between Dowdell Lane and Charter Oak Avenue behind k-rail to prepare for a future traffic shift – Wed & Thur Nights
• Concrete Media shift btwn Dowdell Lane & Charter Oak Ave to close sb shoulder for widening

Hours of work are 7:00 PM to 6:00 AM, Mon-Thur. (No Friday work due to the Memorial Day Holiday). Northbound shoulder HMA paving will take place behind k-rail. Re-striping operations will be behind k-rail with partial re-striping within the current northbound lane. One-way traffic control will be used. Delays of up to 5 minutes are anticipated. Driveway access to and Mills Lane will be limited while these areas are paved.


WEEK STARTING MAY 29, 2016

No work this week. Project is suspended for Wine Auction Week.

ADDITIONAL NOTES AND UPDATES TO THE PROJECT TEAM:
• As stated above, all construction work during Wine Auction Week has been suspended. Skeleton crews will be available for maintenance of existing traffic delineation.
• Full driveway access to the businesses btwn Vidovich & Grayson. Access will be available through entrances and exits along county roads.
• No work is scheduled near Whitehall Lane
• Charter Oak Crosswalk flashing beacon will be out-of-service starting on May 19 as we pave through this area. Portable Changeable Message Signs will be changed to say: “CROSSWALK AHEAD” | “WATCH FOR PEDS”.


For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/

Please be #BeWorkZoneAlert.
# # #

Wednesday, January 27, 2016

SR 29-Channelization Project -Napa - Updates wks Jan 31 & Feb 13

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: January 27, 2016
District: 4 – Oakland
Contact: Vnce Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting Sunday, January 31

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.

Below is the two week project update.

WEEKS STARTING JANUARY 31, 2016 THROUGH FEBRUARY 13, 2016
• Storm water maintenance and erosion control btwn Mee Lane and Charter Oak Avenue
• Traffic delineation maintenance btwn Mee Lane and Charter Oak Avenue

Work is 7:00 AM until 5:00 PM Monday through Friday. No lane closures scheduled.

Night Work
• Sewer repair work on SR-29 from Charter Oak Avenue to Sulphur Creek Bridge

Work is scheduled 9:00 PM until 6:00 AM, Sunday through Thursday. One-way traffic control will be used at Charter Oak Avenue. Delays of up to 5 minutes are expected.

For additional information, see our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/

Or follow Caltrans on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/

Please be #BeWorkZoneAlert.


# # #

Tuesday, January 12, 2016

SR29-Channelization -Napa County - Update wk Jan 12 and Jan 17

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: January 12, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting Tuesday, January 12

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.

Below is the two week project update.

WEEK STARTING JANUARY 12, 2016
• Storm water maintenance and erosion control between Mee Lane and Charter Oak Avenue
• Drainage system work along shoulder at Mills Lane and between Inglewood Avenue and Stice Lane

Work is scheduled 7:00 AM until 5:00 PM, Monday through Friday, weather permitting. No lane closures scheduled. Lanes may be shifted and widths may be reduced in certain work areas for safety. There is no night work scheduled for this week.

WEEK STARTING JANUARY 17, 2016
• Storm water maintenance and erosion control between Mee Lane & Charter Oak Avenue
• Drainage system work along shoulder between Inglewood Avenue and Stice Lane

Work is scheduled 7:00 AM until 5:00 PM, Monday through Friday, weather permitting. No lane closures scheduled. Lanes may be shifted and widths may be reduced in certain work areas for safety. There is no night work scheduled for this week.

See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/

Or follow Caltrans on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/


# # #

Wednesday, December 23, 2015

SR 29-Channelization-Napa County-Updates wks Dec 27 & Jan 3

State of California • Department of Transportation

CONSTRUCTION NOTICE

Date: December 23, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

State Route 29-Channelization Project-Napa County
Updates Starting Sunday, December 27

NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.

Below is the two week update for the project.

WEEK STARTING DECEMBER 27, 2015
Site wide storm water maintenance and erosion control between Mee Lane and Charter Oak Avenue.

Hours of work are scheduled 7:00 AM until 5:00 PM, Monday through Friday. No lane closures are scheduled. Lanes may be shifted and widths may be reduced in certain work areas for safety. No delays to the travelling public are anticipated. No night work is scheduled this week.

WEEK STARTING JANUARY 3, 2016
• Drainage pipe and inlet installation between Stice Lane and Inglewood Avenue in the Southbound Shoulder (Delectus to Del Dotto)

Hours of work are scheduled for 7:00 AM to 5:00 PM, Monday through Friday. No lane closures are scheduled. Lanes may be shifted and widths may be reduced in certain work areas for safety. No delays to the travelling public are anticipated. No night work is scheduled this week.

See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/

Or follow Caltrans on Twitter: http://twitter.com/CaltransD4

For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/


# # #