State of California • Department of Transportation
TRAFFIC ADVISORY
Date: May 10, 2018
District: 4-Oakland
Contact: Vince Jacala
Vince.jacala@dot.ca.gov
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 Between Napa and St. Helena
Overnight One-Way Traffic Controls
Paving Work Begins
Monday, May 21, 2018-Fall 2018
NAPA COUNTY— The California Department of Transportation (Caltrans) is scheduled to begin major roadway pavement work on State Route 29 (SR-29) in Napa County.
This is part of a long-term project to repair the pavement on State Route 29 (SR-29) between Napa and just south of St. Helena. Preliminary drainage work started in March 2018.
The valley temperatures are now warm enough for crews to begin paving 12-miles of SR-29 between north of Trancas Street in Napa and Mee Lane in the County of Napa.
Overnight Work Starts May 21, 2018
Paving work starts Monday, May 21 until fall 2018. Work is scheduled Mondays-Fridays starting at 7:00 PM until 6:00 AM the following mornings. All work is weather permitting
No work is scheduled on the following holiday/regional event dates:
• May 25-May 28, 2018……………...Memorial Day/Bottle Rock
• July 2-July 8, 2018………………… Independence Day
• August 31-September 3, 2018….... Labor Day/Harvest
One-Way Traffic Controls-Expect Delays
To ensure worker and public safety, one-way traffic controls will be in effect during the work on SR-29. Crews will alternate lane closures in both northbound and southbound directions. Motorists should expect delays and allow for extra travel time.
For more, go to our new project website: http://www.dot.ca.gov/d4/29napavalleypavement/
24/7 traffic updates, follow 511.org: https://twitter.com/511SFBAY
Real-time traffic, click-on Caltrans Quick Maps: http://quickmap.dot.ca.gov/
Caltrans thanks you for your patience as we work to maintain California’s highways.
###
Caltrans District 4 - Working to bring you safe, efficient, accessible, and environmentally responsible highways and bridges in the Bay Area.
Showing posts with label #Caltrans #Napa #St.Helena #Hwy29 #29 #update #Helena #Mee. Show all posts
Showing posts with label #Caltrans #Napa #St.Helena #Hwy29 #29 #update #Helena #Mee. Show all posts
Thursday, May 10, 2018
Friday, February 26, 2016
State Route 29 Napa - St. Helena Updates wk of Feb 29
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: February 26, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, February 28
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the two week project update.
WEEK STARTING FEBRUARY 28, 2016
• Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue
• Site-wide storm water pollution prevention maintenance btwn Mee Lane & Charter Oak Avenue
Work is scheduled 7:00 AM until 5:00 PM, Monday-Friday. No daytime closures anticipated.
Night Work
• Underground drainage utility work (Hall Winery) btwn Inglewood Avenue & Sulphur Springs AV
• Curb and gutter reconstruction at Sulphur Springs Avenue
• Sewer repair work at Charter Oak Avenue to Sulphur Creek Bridge
Work for the Charter Oak sewer repair is scheduled 9:00 PM to 6:00 AM, Sunday-Thursday. Underground electrical work at Stice Lane is 7:00 PM until 6:00AM, Monday-Wednesday.
Nighttime one-way traffic control will be in effect. Delays of up to 5 minutes are expected.
WEEK STARTING MARCH 6, 2016
•Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue.
Work is scheduled 7:00 AM until 5:00 PM, Monday-Friday. No daytime closures are scheduled.
For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
CONSTRUCTION NOTICE
Date: February 26, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, February 28
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the two week project update.
WEEK STARTING FEBRUARY 28, 2016
• Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue
• Site-wide storm water pollution prevention maintenance btwn Mee Lane & Charter Oak Avenue
Work is scheduled 7:00 AM until 5:00 PM, Monday-Friday. No daytime closures anticipated.
Night Work
• Underground drainage utility work (Hall Winery) btwn Inglewood Avenue & Sulphur Springs AV
• Curb and gutter reconstruction at Sulphur Springs Avenue
• Sewer repair work at Charter Oak Avenue to Sulphur Creek Bridge
Work for the Charter Oak sewer repair is scheduled 9:00 PM to 6:00 AM, Sunday-Thursday. Underground electrical work at Stice Lane is 7:00 PM until 6:00AM, Monday-Wednesday.
Nighttime one-way traffic control will be in effect. Delays of up to 5 minutes are expected.
WEEK STARTING MARCH 6, 2016
•Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue.
Work is scheduled 7:00 AM until 5:00 PM, Monday-Friday. No daytime closures are scheduled.
For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
Thursday, February 4, 2016
SR-29-Channelization Project-Napa County wks Feb 7 & Feb 14
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: February 4, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, February 7
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the two week project update.
WEEK STARTING FEBRUARY 7, 2016
• Site-wide traffic delineation maintenance between Mee Lane & Charter Oak Avenue.
• Drainage system installation btwn Stice Lane & Inglewood Ave on southbound shoulder.
Work scheduled 7:00 AM to 5:00 PM, Monday-Friday. No daytime closures scheduled.
• Sewer repair work at Charter Oak Avenue to Sulphur Creek Bridge
• Underground electrical work at Stice Lane
Charter Oak sewer repair scheduled 9:00 PM until 6:00 AM, Sunday-Thursday. Underground electrical work at Stice Lane scheduled 7:00 PM to 6:00 AM, Monday-Wednesday. One-way traffic control in effect.
WEEK STARTING FEBRUARY 14, 2016
• Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue.
Work is 7:00 AM to 5:00 PM, Monday through Friday. No lane closures are required.
For additional information, see our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
CONSTRUCTION NOTICE
Date: February 4, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, February 7
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the two week project update.
WEEK STARTING FEBRUARY 7, 2016
• Site-wide traffic delineation maintenance between Mee Lane & Charter Oak Avenue.
• Drainage system installation btwn Stice Lane & Inglewood Ave on southbound shoulder.
Work scheduled 7:00 AM to 5:00 PM, Monday-Friday. No daytime closures scheduled.
• Sewer repair work at Charter Oak Avenue to Sulphur Creek Bridge
• Underground electrical work at Stice Lane
Charter Oak sewer repair scheduled 9:00 PM until 6:00 AM, Sunday-Thursday. Underground electrical work at Stice Lane scheduled 7:00 PM to 6:00 AM, Monday-Wednesday. One-way traffic control in effect.
WEEK STARTING FEBRUARY 14, 2016
• Site-wide traffic delineation maintenance between Mee Lane and Charter Oak Avenue.
Work is 7:00 AM to 5:00 PM, Monday through Friday. No lane closures are required.
For additional information, see our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
Friday, August 28, 2015
State Route 29- Channelization- Napa Co. -Updates Aug 28-Sept 4
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: August 28, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates August 28 until September 4
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday August 28
Crews are scheduled to perform limited work for the week starting August 28 until September 4.
Daytime operations will consist of PG&E performing re-striping work on State Route 29 (SR-29) on Wednesday, September 2. Hours of work are scheduled starting at 6:00AM until 6:00PM. Work will be performed under a lane shift.
*A lane shift occurs when crews slightly shift the location of a traffic lane to perform work in an existing lane. Watch for shifts in the route which are clearly marked.
Railroad signal relocation operations will be performed at the following railroad crossings: Whitehall, Zinfandel, and Stice. Hours of work are scheduled starting at 7:00AM until 5:00PM. Work will be performed with shoulder closures only.
Site maintenance work will be performed from 7:00AM until 3:30PM from Mee Lane to Stice Lane. This work will not require any type of closures. No nighttime work is scheduled starting August 28 until September 4.
*Major roadwork requiring lane closures will be restricted during the harvest season period starting August 15 and ending October 15. PG&E, railroad signal relocation work and maintenance and site cleanup work will continue throughout this period.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
CONSTRUCTION NOTICE
Date: August 28, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates August 28 until September 4
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday August 28
Crews are scheduled to perform limited work for the week starting August 28 until September 4.
Daytime operations will consist of PG&E performing re-striping work on State Route 29 (SR-29) on Wednesday, September 2. Hours of work are scheduled starting at 6:00AM until 6:00PM. Work will be performed under a lane shift.
*A lane shift occurs when crews slightly shift the location of a traffic lane to perform work in an existing lane. Watch for shifts in the route which are clearly marked.
Railroad signal relocation operations will be performed at the following railroad crossings: Whitehall, Zinfandel, and Stice. Hours of work are scheduled starting at 7:00AM until 5:00PM. Work will be performed with shoulder closures only.
Site maintenance work will be performed from 7:00AM until 3:30PM from Mee Lane to Stice Lane. This work will not require any type of closures. No nighttime work is scheduled starting August 28 until September 4.
*Major roadwork requiring lane closures will be restricted during the harvest season period starting August 15 and ending October 15. PG&E, railroad signal relocation work and maintenance and site cleanup work will continue throughout this period.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
Friday, July 10, 2015
SR 29-Channeliz Update-Napa Wk July 13
State of California • Department of Transportation
TRAFFIC ADVISORY
Date:
July 10, 2015
District:
4 Oakland
Contact:
Vince Jacala
Phone:(510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Week starting Monday, July 13
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Construction- Updates Week of July 13
Major construction started in June 2015 and will be completed in 2017.
No work is scheduled on Saturday, July 11 and Sunday, July 12.
Daytime work-starting Monday, July 13
During the week starting Monday, July 13 until Friday, July 17, crews will continue daytime installation of drainage systems adjacent to the roadway on northbound SR-29. Daytime operations will occur Monday through Friday from 7:00AM until 3:30PM. No lane closures are scheduled for daytime work. PG&E will also perform daytime work related to the project.
Nighttime work-starting Tuesday, July 14
Starting Tuesday, July 14 until Friday, July 17 crews will begin nighttime asphalt paving on the shoulder of northbound SR-29 from Mee Lane to Zinfandel Lane. Nighttime operations will occur Tuesday through Friday from 7:00PM until 6:00AM the following mornings. Motorists may encounter delays as crews alternate northbound and southbound traffic on SR-29 onto one lane through the construction zone. Motorists should watch for flaggers. CHP will assist with directing traffic.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
TRAFFIC ADVISORY
Date:
July 10, 2015
District:
4 Oakland
Contact:
Vince Jacala
Phone:(510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Week starting Monday, July 13
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Construction- Updates Week of July 13
Major construction started in June 2015 and will be completed in 2017.
No work is scheduled on Saturday, July 11 and Sunday, July 12.
Daytime work-starting Monday, July 13
During the week starting Monday, July 13 until Friday, July 17, crews will continue daytime installation of drainage systems adjacent to the roadway on northbound SR-29. Daytime operations will occur Monday through Friday from 7:00AM until 3:30PM. No lane closures are scheduled for daytime work. PG&E will also perform daytime work related to the project.
Nighttime work-starting Tuesday, July 14
Starting Tuesday, July 14 until Friday, July 17 crews will begin nighttime asphalt paving on the shoulder of northbound SR-29 from Mee Lane to Zinfandel Lane. Nighttime operations will occur Tuesday through Friday from 7:00PM until 6:00AM the following mornings. Motorists may encounter delays as crews alternate northbound and southbound traffic on SR-29 onto one lane through the construction zone. Motorists should watch for flaggers. CHP will assist with directing traffic.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #