State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: December 11, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, December 13
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the two week update for the project.
WEEK STARTING DECEMBER 13, 2015
• Electrical work at Stice Lane and at Zinfandel Avenue in the Southbound SR-29 Shoulder
• Storm drain system work between Inglewood Avenue and Stice Lane in the Southbound SR-29 Shoulder
• Site-wide storm water maintenance
Hours of work are scheduled for 7:00 AM to 5:00 PM, Monday through Friday. No lane closures are scheduled. Lanes may be shifted and widths may be reduced in certain work areas for safety. No delays to the travelling public are anticipated. No night work is scheduled the week of December 13.
WEEK STARTING DECEMBER 20, 2015
No day work or night work is scheduled the week of December 20.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
Caltrans District 4 - Working to bring you safe, efficient, accessible, and environmentally responsible highways and bridges in the Bay Area.
Friday, December 11, 2015
Tuesday, December 8, 2015
SR-13 NB Onramp @Moraga Av Closed wk of Dec 13 & wk of Dec 21
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: December 8, 2015
District: 4 - Oakland
Contact: Shannon Brinias
Phone: (510) 286-5543
FOR IMMEDIATE RELEASE
Moraga Avenue Storm Damage Repair Project Starts
On-ramp Closures Planned in December
ALAMEDA COUNTY, December 8, 2015 – Caltrans will begin work on Monday December 7 for the first phase of the Moraga Avenue Storm Damage Repair Project. The project will require tree removal for construction of the storm damage repair project adjacent to the Moraga Avenue on-ramp to State Route 13 (SR-13) northbound. The site is bordered on the east by Fernwood Drive.
REVISED: No ramp closures anticipated the week of Monday December 7 through Friday December 11.
Daytime closures for the Moraga Avenue on-ramp will be required for safe placement of construction equipment. Caltrans anticipates the on-ramp to SR-13 NB at Moraga Avenue will be closed on:
Monday December 14 through Friday December 18 from 9:00 AM to 4:00 PM daily.
Monday December 21 through Wednesday December 23 from 9:00 AM to 4:00 PM daily.
Detour signs will re-route drivers to alternate on-ramps. Plans subject to change due to weather. For more info:
http://www.dot.ca.gov/dist4/projects/13storm/
Motorists should drive with caution through the work zone. Get real-time traffic on Caltrans Quickmaps: http://quickmap.dot.ca.gov/ Or follow Caltrans on Twitter: http://twitter.com/CaltransD4 .
Caltrans appreciates your patience as we work to maintain California’s highways.
Please #BeWorkZoneAlert.
###
TRAFFIC ADVISORY
Date: December 8, 2015
District: 4 - Oakland
Contact: Shannon Brinias
Phone: (510) 286-5543
FOR IMMEDIATE RELEASE
Moraga Avenue Storm Damage Repair Project Starts
On-ramp Closures Planned in December
ALAMEDA COUNTY, December 8, 2015 – Caltrans will begin work on Monday December 7 for the first phase of the Moraga Avenue Storm Damage Repair Project. The project will require tree removal for construction of the storm damage repair project adjacent to the Moraga Avenue on-ramp to State Route 13 (SR-13) northbound. The site is bordered on the east by Fernwood Drive.
REVISED: No ramp closures anticipated the week of Monday December 7 through Friday December 11.
Daytime closures for the Moraga Avenue on-ramp will be required for safe placement of construction equipment. Caltrans anticipates the on-ramp to SR-13 NB at Moraga Avenue will be closed on:
Monday December 14 through Friday December 18 from 9:00 AM to 4:00 PM daily.
Monday December 21 through Wednesday December 23 from 9:00 AM to 4:00 PM daily.
Detour signs will re-route drivers to alternate on-ramps. Plans subject to change due to weather. For more info:
http://www.dot.ca.gov/dist4/projects/13storm/
Motorists should drive with caution through the work zone. Get real-time traffic on Caltrans Quickmaps: http://quickmap.dot.ca.gov/ Or follow Caltrans on Twitter: http://twitter.com/CaltransD4 .
Caltrans appreciates your patience as we work to maintain California’s highways.
Please #BeWorkZoneAlert.
###
Monday, December 7, 2015
State Route 12-Laguna de Santa Rosa night closures start Dec 18
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: December 7, 2015
District: 4 - Oakland
Contact: Allyn Amsk
Phone: (510) 286-5445
FOR IMMEDIATE RELEASE
State Route 12 Laguna de Santa Rosa Project
Road Closure and Traffic Shift to New Bridge Scheduled for December 18
SONOMA COUNTY – On Friday night, December 18, Caltrans will close State Route 12 at the Laguna de Santa Rosa Bridge in order to shift traffic to the first half of the new bridge. During this work, residents may notice increased noise from construction and mandatory backup alarms.
• SR 12 at the Laguna de Santa Rosa Bridge will be closed Friday night, December 18, at 10 p.m. and reopen on Saturday morning, December 19, at 7 a.m.
• SR 12 between Morris Street and Llano Road will only be open to local traffic.
• During the full highway closure, Village Park residents will not be permitted to freely enter the highway. Flaggers will control access, and residents should expect delays.
Detour for eastbound SR 12 traffic: Go northbound on Petaluma Avenue, left on McKinley Street, right on North Main Street, left on Route 116/Healdsburg Avenue, right on eastbound Occidental Road, right on southbound Fulton Road, and return to SR 12.
Detour for westbound SR 12 traffic: turn right on Fulton Road, left on Occidental Road, left on SR 116 (North Gravenstein Highway), right on North Main Street, and return to SR 12.
If work is delayed due to weather conditions, it will be rescheduled. Please drive cautiously through the construction zone, leave a safe traveling distance between your vehicle and the vehicle ahead of you, and Slow for the Cone Zone.
Future Construction activities include:
• Traffic shift to the first half of the new bridge
• Demolition of the old bridge
• Build the second half of the new bridge
• This work is expected to take place over two construction seasons and will not be complete until 2017.
Please check the project website at http://www.dot.ca.gov/dist4/12santarosabridge/ for more information.
For more information about Caltrans projects in Sonoma County, visit the webpage at www.dot.ca.gov/dist4 and click on Sonoma County.
###
TRAFFIC ADVISORY
Date: December 7, 2015
District: 4 - Oakland
Contact: Allyn Amsk
Phone: (510) 286-5445
FOR IMMEDIATE RELEASE
State Route 12 Laguna de Santa Rosa Project
Road Closure and Traffic Shift to New Bridge Scheduled for December 18
SONOMA COUNTY – On Friday night, December 18, Caltrans will close State Route 12 at the Laguna de Santa Rosa Bridge in order to shift traffic to the first half of the new bridge. During this work, residents may notice increased noise from construction and mandatory backup alarms.
• SR 12 at the Laguna de Santa Rosa Bridge will be closed Friday night, December 18, at 10 p.m. and reopen on Saturday morning, December 19, at 7 a.m.
• SR 12 between Morris Street and Llano Road will only be open to local traffic.
• During the full highway closure, Village Park residents will not be permitted to freely enter the highway. Flaggers will control access, and residents should expect delays.
Detour for eastbound SR 12 traffic: Go northbound on Petaluma Avenue, left on McKinley Street, right on North Main Street, left on Route 116/Healdsburg Avenue, right on eastbound Occidental Road, right on southbound Fulton Road, and return to SR 12.
Detour for westbound SR 12 traffic: turn right on Fulton Road, left on Occidental Road, left on SR 116 (North Gravenstein Highway), right on North Main Street, and return to SR 12.
If work is delayed due to weather conditions, it will be rescheduled. Please drive cautiously through the construction zone, leave a safe traveling distance between your vehicle and the vehicle ahead of you, and Slow for the Cone Zone.
Future Construction activities include:
• Traffic shift to the first half of the new bridge
• Demolition of the old bridge
• Build the second half of the new bridge
• This work is expected to take place over two construction seasons and will not be complete until 2017.
Please check the project website at http://www.dot.ca.gov/dist4/12santarosabridge/ for more information.
For more information about Caltrans projects in Sonoma County, visit the webpage at www.dot.ca.gov/dist4 and click on Sonoma County.
###
Friday, December 4, 2015
SR 29-Channelization-Napa County-Updates wks Dec 6 & Dec 12
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: December 4, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, December 6
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
The following work is scheduled:
WEEK STARTING DECEMBER 6, 2015
• Roadway excavation in the nb shoulder btwn Vintage Avenue & Dowdell Lane
• Asphalt paving between Stice Lane and Dowdell Lane
Hours of work are 7:00 AM to 5:00 PM, Monday-Friday. No lane closures are scheduled. Lanes may be shifted in certain work areas for safety.
Night Work
• Storm drain crossings at Sulphur Springs Avenue & Mills Lane across Route 29
• Drainage pipe installation in the nb shoulder btwn Vintage Avenue and Mills Lane
• Localized asphalt paving between Stice Lane and Dowdell Lane
Hours of work are scheduled 7:00 PM to 6:00 AM, Monday through Friday. One-way traffic control will be used. Delays of up to 5 minutes are expected.
WEEK STARTING DECEMBER 13, 2015
• Roadway excavation in nb shoulder btwn Dowdell Ln & Charter Oak Avenue
Hours of work are 7:00 AM to 5:00 PM, Monday-Friday. No lane closures are scheduled. Lanes may be shifted and widths reduced in certain work areas for safety.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
CONSTRUCTION NOTICE
Date: December 4, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, December 6
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
The following work is scheduled:
WEEK STARTING DECEMBER 6, 2015
• Roadway excavation in the nb shoulder btwn Vintage Avenue & Dowdell Lane
• Asphalt paving between Stice Lane and Dowdell Lane
Hours of work are 7:00 AM to 5:00 PM, Monday-Friday. No lane closures are scheduled. Lanes may be shifted in certain work areas for safety.
Night Work
• Storm drain crossings at Sulphur Springs Avenue & Mills Lane across Route 29
• Drainage pipe installation in the nb shoulder btwn Vintage Avenue and Mills Lane
• Localized asphalt paving between Stice Lane and Dowdell Lane
Hours of work are scheduled 7:00 PM to 6:00 AM, Monday through Friday. One-way traffic control will be used. Delays of up to 5 minutes are expected.
WEEK STARTING DECEMBER 13, 2015
• Roadway excavation in nb shoulder btwn Dowdell Ln & Charter Oak Avenue
Hours of work are 7:00 AM to 5:00 PM, Monday-Friday. No lane closures are scheduled. Lanes may be shifted and widths reduced in certain work areas for safety.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
Thursday, December 3, 2015
Moraga Avenue-Hwy 13 Onramp Closures-Start Dec 7
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: December 3, 2015
District: 4 - Oakland
Contact: Shannon Brinias
Phone: (510) 286-5543
FOR IMMEDIATE RELEASE
Moraga Avenue Storm Damage Repair Project Starts,
On-ramp Closures Planned in December
ALAMEDA COUNTY, December 3, 2015 – Caltrans will begin work on Monday December 7 for the first phase of the Moraga Avenue Storm Damage Repair Project. The project will require tree removal for construction of the storm damage repair project adjacent to the Moraga Avenue on-ramp to State Route 13 (SR-13) northbound. The site is bordered on the east by Fernwood Drive.
Daytime closures for the Moraga Avenue on-ramp will be required for safe placement of construction equipment. Caltrans anticipates the on-ramp to SR-13 NB at Moraga Avenue will be closed on:
• Monday December 7 through Friday December 11 from 9:00 AM to 4:00 PM daily.
• Monday December 14 through Friday December 18 from 9:00 AM to 4:00 PM daily.
• Monday December 21 through Wednesday December 23 from 9:00 AM to 4:00 PM daily.
Detour signs will re-route drivers to alternate on-ramps. Plans subject to change due to weather. For more info: http://www.dot.ca.gov/dist4/projects/13storm/
Motorists should drive with caution through the work zone. Get real-time traffic on Caltrans Quickmaps: http://quickmap.dot.ca.gov/ Or follow Caltrans on Twitter: http://twitter.com/CaltransD4 .
Caltrans appreciates your patience as we work to maintain California’s highways. Please #BeWorkZoneAlert.
Follow us on Twitter: http://www.twitter.com/CaltransD4
Like us on Facebook: http://www.Facebook.com/CaltransDist4
Caltrans Mission: Provide a safe, sustainable, integrated, and efficient transportation system to enhance California’s economy and livability.
Caltrans Vision: A performance-driven, transparent, and accountable organization that values its people, resources and partners, and meets new challenges through leadership, innovation, and teamwork.
###
Wednesday, December 2, 2015
State Route 1-Lantos Tunnels-Overnight Full Closure Dec 4 at 10PM
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: December 2, 2015
District: 4 - Oakland
Contact: Vince Jacala Contact: Bob Haus
Phone: 510-286-5206 Phone: 510-286-5576
State Route 1-Tom Lantos (Devil’s Slide) Tunnels
Mandatory Emergency Response Drill-Overnight Tunnel Closures
Reminder-Starts-Friday, December 4 at 10:00 PM
SAN MATEO COUNTY – Caltrans will conduct its second annual mandatory emergency response drill at the State Route 1 (SR-1)-Tom Lantos (Devil’s Slide) Tunnels.
The mandatory six-hour emergency response drill begins Friday, December 4 at 10:00PM and concludes Saturday, December 5 at 4:00 AM.
The exercise will take place either rain or shine.
For the safety of crews and the public, all northbound and southbound lanes on SR-1 through the Tom Lantos (Devil’s Slide) Tunnels will be closed during the exercise.
Lantos Tunnel-Detour Routes:
During the tunnel closures, the following detours between Pacifica and Half Moon Bay will be in effect. The California Highway Patrol (CHP) will also help direct motorists:
From Pacifica: North on SR-1 to southbound on Interstate-280 (I-280)
From Half Moon Bay: East on State Route 92 onto northbound I-280
The emergency management exercise will be a coordinated effort including the CHP, San Mateo County Sheriff’s Office, Pacifica Fire and Police Departments, California Office of Emergency Services, Cal-Fire, and other first responders.
During this exercise, there will be fire simulation, crash simulation, and simulated smoke.
For the latest Caltrans information, go to our District website at www.dot.ca.gov/dist4
Or follow us on Twitter at: http://twitter/com/CaltransD4
# # #
TRAFFIC ADVISORY
Date: December 2, 2015
District: 4 - Oakland
Contact: Vince Jacala Contact: Bob Haus
Phone: 510-286-5206 Phone: 510-286-5576
State Route 1-Tom Lantos (Devil’s Slide) Tunnels
Mandatory Emergency Response Drill-Overnight Tunnel Closures
Reminder-Starts-Friday, December 4 at 10:00 PM
SAN MATEO COUNTY – Caltrans will conduct its second annual mandatory emergency response drill at the State Route 1 (SR-1)-Tom Lantos (Devil’s Slide) Tunnels.
The mandatory six-hour emergency response drill begins Friday, December 4 at 10:00PM and concludes Saturday, December 5 at 4:00 AM.
The exercise will take place either rain or shine.
For the safety of crews and the public, all northbound and southbound lanes on SR-1 through the Tom Lantos (Devil’s Slide) Tunnels will be closed during the exercise.
Lantos Tunnel-Detour Routes:
During the tunnel closures, the following detours between Pacifica and Half Moon Bay will be in effect. The California Highway Patrol (CHP) will also help direct motorists:
From Pacifica: North on SR-1 to southbound on Interstate-280 (I-280)
From Half Moon Bay: East on State Route 92 onto northbound I-280
The emergency management exercise will be a coordinated effort including the CHP, San Mateo County Sheriff’s Office, Pacifica Fire and Police Departments, California Office of Emergency Services, Cal-Fire, and other first responders.
During this exercise, there will be fire simulation, crash simulation, and simulated smoke.
For the latest Caltrans information, go to our District website at www.dot.ca.gov/dist4
Or follow us on Twitter at: http://twitter/com/CaltransD4
# # #
Tuesday, December 1, 2015
State Route 29/Sonoma Blvd-Vallejo-Maintenance Partership-Lane Closures Dec 2
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: December 1, 2015
Agency: Caltrans District 4
Contact: Vince Jacala
Phone: (510) 286-5206
Agency: City of Vallejo
Contact: Mike Schreiner
Phone: (707) 648-4319
FOR IMMEDIATE RELEASE
Caltrans and City of Vallejo Partner in Major Maintenance Effort
State Route 29/Sonoma Boulevard at Redwood Street
Lane Closures during Landscape & Litter Effort on Wednesday, December 2
SOLANO COUNTY – Caltrans and the City of Vallejo join forces in the latest phase of a key partnership to beautify main entrances and thoroughfares in Vallejo through the “Vallejo Interagency Partnership” (VIP) program.
The major landscaping maintenance and litter cleanup effort includes work on northbound and southbound State Route 29 (SR-29)/Sonoma Boulevard between Couch Street/Mississippi Street and Redwood Street. All work is weather permitting.
The major maintenance effort starts Wednesday, December 2 at 8:00 AM until 2:00 PM.
Crews from Caltrans and the City of Vallejo will trim-back overgrown shrubs, weed, mow, and clear-out trash, and debris along SR-29/Sonoma Boulevard.
Lane Closures on State Route 29/Sonoma Boulevard
To ensure worker and public safety, the far left lanes of northbound and southbound SR-29 between Couch Street/Mississippi and Redwood Street will be closed during the work. One traffic lane in each direction will remain open at all times.
Motorists headed onto eastbound Redwood Street from northbound SR-29/Sonoma Boulevard will also be detoured to Sereno Drive and Broadway, then back onto Redwood Street.
Detour signs will be posted. Please allow extra travel time and watch for crews working in medians and shoulders. We appreciate your patience as we work to maintain our highways.
For additional information, go to our project webpage at: http://www.dot.ca.gov/dist4/projects/VIP/
Or follow Caltrans on Twitter at:
https://mobile.twitter.com/CaltransD4
# # #
TRAFFIC ADVISORY
Date: December 1, 2015
Agency: Caltrans District 4
Contact: Vince Jacala
Phone: (510) 286-5206
Agency: City of Vallejo
Contact: Mike Schreiner
Phone: (707) 648-4319
FOR IMMEDIATE RELEASE
Caltrans and City of Vallejo Partner in Major Maintenance Effort
State Route 29/Sonoma Boulevard at Redwood Street
Lane Closures during Landscape & Litter Effort on Wednesday, December 2
SOLANO COUNTY – Caltrans and the City of Vallejo join forces in the latest phase of a key partnership to beautify main entrances and thoroughfares in Vallejo through the “Vallejo Interagency Partnership” (VIP) program.
The major landscaping maintenance and litter cleanup effort includes work on northbound and southbound State Route 29 (SR-29)/Sonoma Boulevard between Couch Street/Mississippi Street and Redwood Street. All work is weather permitting.
The major maintenance effort starts Wednesday, December 2 at 8:00 AM until 2:00 PM.
Crews from Caltrans and the City of Vallejo will trim-back overgrown shrubs, weed, mow, and clear-out trash, and debris along SR-29/Sonoma Boulevard.
Lane Closures on State Route 29/Sonoma Boulevard
To ensure worker and public safety, the far left lanes of northbound and southbound SR-29 between Couch Street/Mississippi and Redwood Street will be closed during the work. One traffic lane in each direction will remain open at all times.
Motorists headed onto eastbound Redwood Street from northbound SR-29/Sonoma Boulevard will also be detoured to Sereno Drive and Broadway, then back onto Redwood Street.
Detour signs will be posted. Please allow extra travel time and watch for crews working in medians and shoulders. We appreciate your patience as we work to maintain our highways.
For additional information, go to our project webpage at: http://www.dot.ca.gov/dist4/projects/VIP/
Or follow Caltrans on Twitter at:
https://mobile.twitter.com/CaltransD4
# # #