TRAFFIC ADVISORY
Today’s Date: October 19, 2015
District: District 4, Oakland
Contact: Bernard Walik
Phone: 510.286.5705
FOR IMMEDIATE RELEASE
STATE ROUTE 237 PAVEMENT REHABILITATION PROJECT
Santa Clara County- The California Department of Transportation (Caltrans) has started a project in Santa Clara County to grind and repave a portion of State Route 237 from North Fair Oaks Avenue in Sunnyvale to North First Street overcrossing in San Jose. The project will also install electrical loop systems on various ramps. The project is expected to be completed in November, 2015.
There will be intermittent ramp lane and ramp closures throughout the project; however, Caltrans will never close two consecutive ramp. The work schedule starts no earlier than 8:00 p.m. and ends by 5:00 a.m. the following day. Caltrans will provide at least one open lane at all times.
The schedule for this week is as follows:
Monday 10/19 (no work scheduled)
Tuesday 10/20 (no work scheduled)
Wednesday 10/21 (8:00 p.m. to 5:00 a.m.)
Thursday 10/22 (no work scheduled)
Friday 10/23 (8:00 p.m. to 5:00 a.m.)
For project questions please contact:
Bernard Walik at 510-286-5705 or email at: Bernard_Walik@dot.ca.gov
You can also follow us on our website at: http://www.dot.ca.gov/dist4/237pavementrehab
###
Caltrans District 4 - Working to bring you safe, efficient, accessible, and environmentally responsible highways and bridges in the Bay Area.
Showing posts with label #project. Show all posts
Showing posts with label #project. Show all posts
Monday, October 19, 2015
Monday, October 5, 2015
I-680 Rehabilitation Project-Fairfield-Benicia Update Week of Oct 5
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: October 5, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680 - Rehabilitation Project
Between Fairfield and Benicia-Update Week of October 5
SOLANO COUNTY – Caltrans is continuing construction of the Interstate 680 (I-680) Rehabilitation Project in Solano County which will rehabilitate and repave approximately 13 miles of northbound and southbound I-680 between Fairfield and Benicia.
Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to repave I-680 with intermittent, overnight, alternating ramp and lane closures. Specific ramp closure and detour signs will be posted.
All work is weather permitting. The project will be completed as early as spring 2016.
I-680 Construction – Week of Monday, October 5
Starting Monday, October 5 until Monday, October 12 crews are scheduled to pave the shoulders of northbound I-680. To ensure worker and public safety, one of the two traffic lanes on northbound I-680 between Fairfield & Benicia will be closed nightly, Mondays through Fridays from 8:00 PM until 4:00 AM the following mornings.
*Motorists should drive with caution and watch for some uneven shoulders and sections of roadway as construction continues.
Paving crews are scheduled to complete final paving of southbound I-680 at a future date.
For additional project information: http://www.dot.ca.gov/dist4/680solanorehab
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans thanks you for your patience as we work to maintain California’s highways. Please #BeWorkZoneAlert
# # #
TRAFFIC ADVISORY
Date: October 5, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680 - Rehabilitation Project
Between Fairfield and Benicia-Update Week of October 5
SOLANO COUNTY – Caltrans is continuing construction of the Interstate 680 (I-680) Rehabilitation Project in Solano County which will rehabilitate and repave approximately 13 miles of northbound and southbound I-680 between Fairfield and Benicia.
Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to repave I-680 with intermittent, overnight, alternating ramp and lane closures. Specific ramp closure and detour signs will be posted.
All work is weather permitting. The project will be completed as early as spring 2016.
I-680 Construction – Week of Monday, October 5
Starting Monday, October 5 until Monday, October 12 crews are scheduled to pave the shoulders of northbound I-680. To ensure worker and public safety, one of the two traffic lanes on northbound I-680 between Fairfield & Benicia will be closed nightly, Mondays through Fridays from 8:00 PM until 4:00 AM the following mornings.
*Motorists should drive with caution and watch for some uneven shoulders and sections of roadway as construction continues.
Paving crews are scheduled to complete final paving of southbound I-680 at a future date.
For additional project information: http://www.dot.ca.gov/dist4/680solanorehab
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans thanks you for your patience as we work to maintain California’s highways. Please #BeWorkZoneAlert
# # #