State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: May 5, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, May 8
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County Below is the week-ahead project update for the week of May 8 and May 15.
WEEK STARTING MAY 8, 2016-Daytime Work
• Roadway excavation and subgrade compaction between Dowdell Lane and Charter Oak Avenue in the northbound shoulder
• Conduit and pole foundation installation for the Grayson Intersection Signal
• Storm drain installation between Stice Lane and Dowdell Lane in the southbound shoulder
Hours of work are 7:00 AM to 5:00 PM, Monday-Friday. Northbound shoulder work primarily behind temporary railing (k-rail). Southbound shoulder work behind portable delineators or traffic cones. No daytime lane closures scheduled. Slower traffic anticipated due to use of heavy equipment. No night work scheduled.
WEEK STARTING MAY 15, 2016-Daytime Work
• Curb and gutter construction btwn Dowdell Lane & Charter Oak Avenue in northbound shoulder
• Roadway compaction btwn Dowdell Lane and Charter Oak Avenue in the northbound shoulder
• Storm drain installation between Stice Lane and Dowdell Lane in the southbound shoulder
• Roadway excavation between Stice Lane and Chaix Lane in the southbound shoulder
Work is 7:00AM-5:00PM, Mon-Fri. No lane closures scheduled. No night work scheduled.
For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
Caltrans District 4 - Working to bring you safe, efficient, accessible, and environmentally responsible highways and bridges in the Bay Area.
Showing posts with label #Caltrans #St.Helena #Napa #Highway29 #29 #SR29 #channelization #Zinfandel #Stice. Show all posts
Showing posts with label #Caltrans #St.Helena #Napa #Highway29 #29 #SR29 #channelization #Zinfandel #Stice. Show all posts
Thursday, May 5, 2016
Friday, April 22, 2016
State Route 29-Channelization Project-Updates wk of April 24
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: April 22, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, April 24
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the week-ahead project update.
WEEK STARTING APRIL 24-April 30, 2016
Day Work
• Roadway excavation and compaction btwn Dowdell LN & Charter Oak Ave on northbound SR-29.
• Storm drain construction between Stice Lane and Dowdell Lane on southbound SR-29.
Work is scheduled 7:00 AM to 5:00 PM, Wed through Fri. No daytime lane closures anticipated.
Night Work
• Temporary re-striping to shift northbound traffic to the center channelization lane. Re-striping is between Mee Lane to Charter Oak Avenue – Monday & Tuesday nights
• Installation of temporary railing (k-rail) between Dowdell LN and Charter Oak AV – Wed night
Work is scheduled 7:00 PM to 6:00 AM, Monday evening through Thursday morning. One-way traffic control will in effect. Delays of up to 5 minutes are expected. Left-turn movements from southbound 29 onto Mills Lane may be limited.
Although the lane shift will primarily be between Dowdell Lane and Charter Oak for the k-rail placement, the temporary striping will encompass the entire length of the project. This is necessary as crews will need to transition to two lanes and other temporary striping work.
For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
CONSTRUCTION NOTICE
Date: April 22, 2016
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, April 24
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Below is the week-ahead project update.
WEEK STARTING APRIL 24-April 30, 2016
Day Work
• Roadway excavation and compaction btwn Dowdell LN & Charter Oak Ave on northbound SR-29.
• Storm drain construction between Stice Lane and Dowdell Lane on southbound SR-29.
Work is scheduled 7:00 AM to 5:00 PM, Wed through Fri. No daytime lane closures anticipated.
Night Work
• Temporary re-striping to shift northbound traffic to the center channelization lane. Re-striping is between Mee Lane to Charter Oak Avenue – Monday & Tuesday nights
• Installation of temporary railing (k-rail) between Dowdell LN and Charter Oak AV – Wed night
Work is scheduled 7:00 PM to 6:00 AM, Monday evening through Thursday morning. One-way traffic control will in effect. Delays of up to 5 minutes are expected. Left-turn movements from southbound 29 onto Mills Lane may be limited.
Although the lane shift will primarily be between Dowdell Lane and Charter Oak for the k-rail placement, the temporary striping will encompass the entire length of the project. This is necessary as crews will need to transition to two lanes and other temporary striping work.
For additional information: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
Please be #BeWorkZoneAlert.
# # #
Wednesday, November 18, 2015
State Route 29-Channelization-Updates Wk of Nov 22
State of California • Department of Transportation
CONSTRUCTION UPDATE
Date: November 18, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, November 22
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
The following work is scheduled:
WEEK STARTING NOVEMBER 22, 2015
• Roadway widening excavation nb shoulder between Chaix Lane & Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane
Work scheduled 7:00 AM to 3:30 PM, Monday through Wednesday. No lane closures scheduled. Lanes may be shifted and widths may be reduced for safety. No night work scheduled. No work on Thursday, November 26 (Thanksgiving) or Friday, November 27.
WEEK STARTING NOVEMBER 29, 2015
• Roadway widening excavation northbound shoulder between Chaix Lane and Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane
• Asphalt widening paving between Stice Lane and Dowdell Lane
Work scheduled 7:00 AM to 3:30 PM, Monday through Friday. No lane closures scheduled.
Night Work
• Underground drainage pipe crossings and drainage inlets at the following locations: Sulphur Springs Avenue and Mill Lane within the Route 29 traveled way.
Work scheduled 7:00 PM to 6:00 AM, Monday through Friday. One-way traffic control will be used. Delays of up to 5 minutes expected.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
CONSTRUCTION UPDATE
Date: November 18, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates Starting Sunday, November 22
NAPA COUNTY – Caltrans and its local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
The following work is scheduled:
WEEK STARTING NOVEMBER 22, 2015
• Roadway widening excavation nb shoulder between Chaix Lane & Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane
Work scheduled 7:00 AM to 3:30 PM, Monday through Wednesday. No lane closures scheduled. Lanes may be shifted and widths may be reduced for safety. No night work scheduled. No work on Thursday, November 26 (Thanksgiving) or Friday, November 27.
WEEK STARTING NOVEMBER 29, 2015
• Roadway widening excavation northbound shoulder between Chaix Lane and Dowdell Lane
• Installation of underground lighting conduits and service equipment in the southbound shoulder at West Zinfandel Lane and Stice Lane
• Asphalt widening paving between Stice Lane and Dowdell Lane
Work scheduled 7:00 AM to 3:30 PM, Monday through Friday. No lane closures scheduled.
Night Work
• Underground drainage pipe crossings and drainage inlets at the following locations: Sulphur Springs Avenue and Mill Lane within the Route 29 traveled way.
Work scheduled 7:00 PM to 6:00 AM, Monday through Friday. One-way traffic control will be used. Delays of up to 5 minutes expected.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
Friday, September 25, 2015
Construction Update-SR 29 Napa County-Channelization-wk of 9-25
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: September 25, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates for week starting Sunday, September 27
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
There will be limited project-related utility work starting Sunday, September 27 until Friday, October 2.
AT&T will perform work within the project limits to remove remaining utility poles and abandoned underground cabling. This work was originally intended for the week starting September 13, 2015 but has been moved to the week of September 27.
Daytime Work-Starting Sunday, September 27
AT&T will remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to charter Oak Avenue. Work will be primarily in the southbound shoulder. Hours of work are 8:00 AM until 3:00 PM.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM until 3:30 PM between Mee Lane to Stice Lane. Work includes storm water pollution prevention and site management. Work will not require any traffic lane closures.
No night work is scheduled this week.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
CONSTRUCTION NOTICE
Date: September 25, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates for week starting Sunday, September 27
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
There will be limited project-related utility work starting Sunday, September 27 until Friday, October 2.
AT&T will perform work within the project limits to remove remaining utility poles and abandoned underground cabling. This work was originally intended for the week starting September 13, 2015 but has been moved to the week of September 27.
Daytime Work-Starting Sunday, September 27
AT&T will remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to charter Oak Avenue. Work will be primarily in the southbound shoulder. Hours of work are 8:00 AM until 3:00 PM.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM until 3:30 PM between Mee Lane to Stice Lane. Work includes storm water pollution prevention and site management. Work will not require any traffic lane closures.
No night work is scheduled this week.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to:
http://www.countyofnapa.org/
# # #
Wednesday, September 16, 2015
State Route 29-Channelization Project-Napa Co. Updates wk Sept 20
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: September 16, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates for week starting Sunday, September 20
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
There will be limited Caltrans work starting Sunday, September 20 until Friday, September 25. AT&T will perform work within the project limits to remove remaining utility poles and abandoned underground cabling. This work was originally intended for the week start September 13, 2015 but has been moved to the week of September 20.
Daytime Work-Starting Sunday, September 20
AT&T will remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to charter Oak Avenue. Work will be primarily in the southbound shoulder. Work will be performed under a lane shift when necessary. Hours of work are scheduled for 8:00 AM to 3:00 PM. This work is being done under a utilities permit.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM to 3:30 PM between Mee Lane to Stice Lane. This work will include storm water pollution prevention maintenance and cleaning of existing culverts. This work will not require any type of closures and should have no effect on traffic. No night work is scheduled for this week.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/
# # #
CONSTRUCTION NOTICE
Date: September 16, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29-Channelization Project-Napa County
Updates for week starting Sunday, September 20
NAPA COUNTY – Caltrans and its local stakeholders have started construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
There will be limited Caltrans work starting Sunday, September 20 until Friday, September 25. AT&T will perform work within the project limits to remove remaining utility poles and abandoned underground cabling. This work was originally intended for the week start September 13, 2015 but has been moved to the week of September 20.
Daytime Work-Starting Sunday, September 20
AT&T will remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to charter Oak Avenue. Work will be primarily in the southbound shoulder. Work will be performed under a lane shift when necessary. Hours of work are scheduled for 8:00 AM to 3:00 PM. This work is being done under a utilities permit.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM to 3:30 PM between Mee Lane to Stice Lane. This work will include storm water pollution prevention maintenance and cleaning of existing culverts. This work will not require any type of closures and should have no effect on traffic. No night work is scheduled for this week.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
For updates on county roads near SR-29 and maintained by the County of Napa go to: http://www.countyofnapa.org/
# # #
Friday, September 11, 2015
State Route 29 -Channelization Project- Napa Co- Updates Sept 11
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: September 11, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
State Route 29 - Channelization Project - Napa County
Updates September 11 until September 18
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work – Friday September 11 until Friday September 18
AT&T is scheduled to remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to Charter Oak Avenue. Work will be primarily on the southbound shoulder. Work will be performed under a lane shift when necessary. Work is scheduled 8:00 AM until 3:00 PM. This work is being done under a utilities permit.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM to 3:30 PM for areas from Mee Lane to Stice Lane. This work will not require any type of closures and should have no effect on traffic. No night work is scheduled for this week.
*Major roadwork requiring lane closures will be restricted during the harvest season period starting August 15 and ending October 15. PG&E, railroad signal relocation work and maintenance and site cleanup work will continue throughout this period.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
Project Benefits
The Highway 29 Channelization Project will rehabilitate the pavement, widen the shoulders, construct a two-way left turn lane, and improve the bicycle/highway/railroad crossing at Whitehall Lane. The project limits are in the Napa County city of St. Helena between Mee Lane and Charter Oak Avenue.
Caltrans thanks you for your patience as we improve California’s highways.
# # #
CONSTRUCTION NOTICE
Date: September 11, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
State Route 29 - Channelization Project - Napa County
Updates September 11 until September 18
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work – Friday September 11 until Friday September 18
AT&T is scheduled to remove remaining utility poles and abandoned underground cabling from Zinfandel Avenue to Charter Oak Avenue. Work will be primarily on the southbound shoulder. Work will be performed under a lane shift when necessary. Work is scheduled 8:00 AM until 3:00 PM. This work is being done under a utilities permit.
Site maintenance work will be performed daily by Caltrans contractors from 7:00 AM to 3:30 PM for areas from Mee Lane to Stice Lane. This work will not require any type of closures and should have no effect on traffic. No night work is scheduled for this week.
*Major roadwork requiring lane closures will be restricted during the harvest season period starting August 15 and ending October 15. PG&E, railroad signal relocation work and maintenance and site cleanup work will continue throughout this period.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
Project Benefits
The Highway 29 Channelization Project will rehabilitate the pavement, widen the shoulders, construct a two-way left turn lane, and improve the bicycle/highway/railroad crossing at Whitehall Lane. The project limits are in the Napa County city of St. Helena between Mee Lane and Charter Oak Avenue.
Caltrans thanks you for your patience as we improve California’s highways.
# # #
Friday, August 14, 2015
State Route 29- St. Helena - Traffic Shift - Aug 14
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: August 13, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Utility Work-Traffic Shift - Expect Delays
Friday, August 14
6:00 AM - 8:30 PM
NAPA COUNTY – Caltrans and its local stakeholders are working closely with local utility companies on the construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
As part of the preliminary work on the project, utility gas line relocation is scheduled on Friday, August 14 starting at 6:00 AM until 8:30 PM. The undergrounding of the gas lines along SR-29 will conducted by PG&E.
Temporary Traffic Shift - August 14
For worker and public safety during the work, traffic lanes on northbound and southbound SR-29 will be slightly shifted near SR-29 at Inglewood Avenue, and SR-29 at Charter Oak Avenue on Friday, August 14.
The northbound SR-29 traffic lane and southbound SR-29 traffic lane will remain open. However, motorists may encounter delays while flaggers intermittently slow traffic for local access at various locations during the temporary traffic shift.
All work is weather permitting. Motorists should drive with caution, watch for flaggers, and expect delays.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
Caltrans thanks you for your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
# # #
TRAFFIC ADVISORY
Date: August 13, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Utility Work-Traffic Shift - Expect Delays
Friday, August 14
6:00 AM - 8:30 PM
NAPA COUNTY – Caltrans and its local stakeholders are working closely with local utility companies on the construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
As part of the preliminary work on the project, utility gas line relocation is scheduled on Friday, August 14 starting at 6:00 AM until 8:30 PM. The undergrounding of the gas lines along SR-29 will conducted by PG&E.
Temporary Traffic Shift - August 14
For worker and public safety during the work, traffic lanes on northbound and southbound SR-29 will be slightly shifted near SR-29 at Inglewood Avenue, and SR-29 at Charter Oak Avenue on Friday, August 14.
The northbound SR-29 traffic lane and southbound SR-29 traffic lane will remain open. However, motorists may encounter delays while flaggers intermittently slow traffic for local access at various locations during the temporary traffic shift.
All work is weather permitting. Motorists should drive with caution, watch for flaggers, and expect delays.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Follow us on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
Caltrans thanks you for your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
# # #
Friday, July 31, 2015
State Route 29-Channelization- Napa County-Updates July 31-Aug 7
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: July 31, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates Friday July 31 until Friday August 7
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday July 31
Starting Friday July 31 until Friday August 7, crews are scheduled to continue daytime excavation work on the highway shoulder of northbound and southbound SR-29 between Whitehall Lane and Stice Lane. Additional work includes installation of waterlines and railroad signal work. Daytime operations will occur Monday through Friday from 7:00 AM until 3:30 PM. No lane closures are scheduled for daytime work.
However, the public may see intermittent delays at the county road intersections due to the railroad signal work. Utility companies will also continue with daytime work in the area related to the project.
Nighttime work - starting Friday July 31
No nighttime work is scheduled starting Friday July 31 through Friday August 7.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
CONSTRUCTION NOTICE
Date: July 31, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates Friday July 31 until Friday August 7
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday July 31
Starting Friday July 31 until Friday August 7, crews are scheduled to continue daytime excavation work on the highway shoulder of northbound and southbound SR-29 between Whitehall Lane and Stice Lane. Additional work includes installation of waterlines and railroad signal work. Daytime operations will occur Monday through Friday from 7:00 AM until 3:30 PM. No lane closures are scheduled for daytime work.
However, the public may see intermittent delays at the county road intersections due to the railroad signal work. Utility companies will also continue with daytime work in the area related to the project.
Nighttime work - starting Friday July 31
No nighttime work is scheduled starting Friday July 31 through Friday August 7.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
Friday, July 24, 2015
State Route 29 - Napa County - Channelization Updates July 24
State of California • Department of Transportation
CONSTRUCTION NOTICE
Date: July 24, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates Friday July 24 until Friday July 31
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday July 24
Starting Friday July 24 until Friday July 31, crews are scheduled to perform daytime excavation work on the highway shoulder of northbound and southbound SR-29 between Whitehall Lane and Stice Lane. Additional work includes installation of waterlines and underground electrical work. Daytime operations will occur Monday through Friday from 7:00 AM until 3:30 PM. No lane closures are scheduled for daytime work. Utility companies will also perform daytime work in the area related to the project.
Nighttime work - starting Friday July 24
Starting Friday July 24 through Friday July 31 crews will perform nighttime asphalt paving on the shoulder of northbound SR-29 from Zinfandel Lane to Stice Lane.
Nighttime operations will occur Monday through Thursday from 7:00 PM until 6:00 AM the following mornings. Friday work will occur from 7:00 PM until 8:00 AM the following morning. Motorists may encounter delays as crews alternate northbound and southbound traffic on SR-29 onto one lane through the construction zone. Motorists should watch for flaggers. CHP will assist with directing traffic.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
CONSTRUCTION NOTICE
Date: July 24, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
State Route 29 - Channelization Project - Napa County
Updates Friday July 24 until Friday July 31
NAPA COUNTY – Caltrans and local stakeholders are continuing construction of the State Route 29 (SR-29) Channelization Project in and near St. Helena in Napa County.
Daytime work - starting Friday July 24
Starting Friday July 24 until Friday July 31, crews are scheduled to perform daytime excavation work on the highway shoulder of northbound and southbound SR-29 between Whitehall Lane and Stice Lane. Additional work includes installation of waterlines and underground electrical work. Daytime operations will occur Monday through Friday from 7:00 AM until 3:30 PM. No lane closures are scheduled for daytime work. Utility companies will also perform daytime work in the area related to the project.
Nighttime work - starting Friday July 24
Starting Friday July 24 through Friday July 31 crews will perform nighttime asphalt paving on the shoulder of northbound SR-29 from Zinfandel Lane to Stice Lane.
Nighttime operations will occur Monday through Thursday from 7:00 PM until 6:00 AM the following mornings. Friday work will occur from 7:00 PM until 8:00 AM the following morning. Motorists may encounter delays as crews alternate northbound and southbound traffic on SR-29 onto one lane through the construction zone. Motorists should watch for flaggers. CHP will assist with directing traffic.
See our project webpage: http://www.dot.ca.gov/dist4/projects/NAP29Channelization/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
For information on county roads near SR-29 & maintained by the County of Napa go to:
http://www.countyofnapa.org/publicworks/
# # #
Subscribe to:
Posts (Atom)