State of California • Department of Transportation
TRAFFIC ADVISORY
Date: July 24, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: (510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680 - Rehabilitation Project
Between Fairfield and Benicia-Update for July 24 - July 31
SOLANO COUNTY – Caltrans is continuing construction of the Interstate 680 (I-680) Rehabilitation Project in Solano County which will rehabilitate and repave approximately 13 miles of northbound and southbound I-680 between Fairfield and Benicia.
Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to repave I-680 with intermittent, overnight, alternating ramp and lane closures. Specific ramp closure and detour signs will be posted.
All work is weather permitting. The project will be completed as early as spring 2016.
I-680 Construction - Friday July 24 until Friday July 31
Starting Friday July 24 until Friday July 31 crews are scheduled to perform electrical work and median guardrail work on southbound and northbound I-680 nightly, Mondays through Fridays, between Fairfield and Benicia.
Paving crews will return in early August to complete the second phase of paving northbound and southbound I-680. Motorists should drive with caution as they may encounter some uneven sections of roadway as construction continues.
To ensure worker and public safety, one of the two traffic lanes on southbound
I-680 between Fairfield & Benicia will be closed nightly, Mondays through Fridays from 8:00 PM until 4:00 AM the following mornings.
Caltrans will also continue to close one of the two traffic lanes on northbound I-680 between Fairfield and Benicia nightly, Mondays through Fridays, from 10:00 PM until 6:00 AM the following mornings.
Watch for our I-680 Solano project webpage coming soon to the Caltrans website: http://www.dot.ca.gov/dist4/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
# # #
Caltrans District 4 - Working to bring you safe, efficient, accessible, and environmentally responsible highways and bridges in the Bay Area.
Showing posts with label #Caltrans #Solano #Benicia #Fairfield #I680 #680 #Rehabilitation #rehab. Show all posts
Showing posts with label #Caltrans #Solano #Benicia #Fairfield #I680 #680 #Rehabilitation #rehab. Show all posts
Friday, July 24, 2015
Wednesday, July 8, 2015
I-680 Between Fairfield & Benicia-Nighttime Lane Closures wk July 8
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: July 8, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: 510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680-Rehabilitation Project
Between Fairfield and Benicia-Update Week of July 8
SOLANO COUNTY– Caltrans is continuing construction of the Interstate 680 (I-680) Rehabilitation Project in Solano County which will rehabilitate and repave approximately 13-miles of northbound and southbound I-680 between Fairfield and Benicia.
Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to repave I-680 with intermittent, overnight, alternating ramp and lane closures. Specific ramp closure and detour signs will be posted.
All work is weather permitting. The project will be completed as early as spring 2016.
I-680 Construction-Week of July 8
During the week starting Wednesday, July 8 until Friday, July 10 crews are scheduled to pave southbound and northbound I-680 nightly between Fairfield and Benicia.
To ensure worker and public safety, one of the two traffic lanes on southbound
I-680 between Fairfield & Benicia will be closed nightly at 8:00PM until 4:00AM the following mornings.
Caltrans will also close one of the two traffic lanes on northbound I-680 between Fairfield and Benicia nightly at 10:00PM until 6:00am the following mornings.
Watch for our I-680 Solano project webpage coming soon to the Caltrans website: http://www.dot.ca.gov/dist4/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
# # #
TRAFFIC ADVISORY
Date: July 8, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: 510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680-Rehabilitation Project
Between Fairfield and Benicia-Update Week of July 8
SOLANO COUNTY– Caltrans is continuing construction of the Interstate 680 (I-680) Rehabilitation Project in Solano County which will rehabilitate and repave approximately 13-miles of northbound and southbound I-680 between Fairfield and Benicia.
Although no full highway closures are scheduled at this time, motorists may experience delays as crews work to repave I-680 with intermittent, overnight, alternating ramp and lane closures. Specific ramp closure and detour signs will be posted.
All work is weather permitting. The project will be completed as early as spring 2016.
I-680 Construction-Week of July 8
During the week starting Wednesday, July 8 until Friday, July 10 crews are scheduled to pave southbound and northbound I-680 nightly between Fairfield and Benicia.
To ensure worker and public safety, one of the two traffic lanes on southbound
I-680 between Fairfield & Benicia will be closed nightly at 8:00PM until 4:00AM the following mornings.
Caltrans will also close one of the two traffic lanes on northbound I-680 between Fairfield and Benicia nightly at 10:00PM until 6:00am the following mornings.
Watch for our I-680 Solano project webpage coming soon to the Caltrans website: http://www.dot.ca.gov/dist4/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
# # #
Monday, May 4, 2015
I-680 Rehab Project- Solano County-Construction Starts wk of May 11
State of California • Department of Transportation
TRAFFIC ADVISORY
Date: May 4, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: 510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680-Between Fairfield and Benicia
Rehabilitation Project
Overnight Intermittent Ramp and Lane Closures
Tentatively Start Week of May 11
SOLANO COUNTY– Caltrans has started preliminary work on the Interstate 680 (I-680) Rehabilitation Project in Solano County, and is scheduled to start major construction the week of May 11. The project will rehabilitate and repave approximately 13-miles of northbound and southbound I-680 between Fairfield and Benicia.
I-680 is a heavily traveled route between the Bay Area and Sacramento.
Construction- Tentatively starts mid-May
Major construction activities are tentatively scheduled to start the week of May 11 and be completed as early as spring 2016.
Although no full highway closures are scheduled at this time, drivers may experience delays as crews work to repave I-680 with intermittent overnight alternating ramp and lane closures in effect during construction. Regular project construction hours will be between 8:00 PM and 6:00 AM. All work is weather permitting.
Caltrans will make an announcement once additional project information is available.
Watch for our project webpage coming soon to the Caltrans website: http://www.dot.ca.gov/dist4/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.
Please #BeWorkZoneAlert
###
TRAFFIC ADVISORY
Date: May 4, 2015
District: 4 – Oakland
Contact: Vince Jacala
Phone: 510) 286-5206
FOR IMMEDIATE RELEASE
Interstate 680-Between Fairfield and Benicia
Rehabilitation Project
Overnight Intermittent Ramp and Lane Closures
Tentatively Start Week of May 11
SOLANO COUNTY– Caltrans has started preliminary work on the Interstate 680 (I-680) Rehabilitation Project in Solano County, and is scheduled to start major construction the week of May 11. The project will rehabilitate and repave approximately 13-miles of northbound and southbound I-680 between Fairfield and Benicia.
I-680 is a heavily traveled route between the Bay Area and Sacramento.
Construction- Tentatively starts mid-May
Major construction activities are tentatively scheduled to start the week of May 11 and be completed as early as spring 2016.
Although no full highway closures are scheduled at this time, drivers may experience delays as crews work to repave I-680 with intermittent overnight alternating ramp and lane closures in effect during construction. Regular project construction hours will be between 8:00 PM and 6:00 AM. All work is weather permitting.
Caltrans will make an announcement once additional project information is available.
Watch for our project webpage coming soon to the Caltrans website: http://www.dot.ca.gov/dist4/
Or follow Caltrans on Twitter: http://twitter.com/CaltransD4
Caltrans appreciates your patience as we work to improve California’s highways.