TRAFFIC ADVISORY

Date: May 16, 2016
District: 4-Oakland
Contact: Vince Jacala
Phone: (510) 286-5206

FOR IMMEDIATE RELEASE

Eastbound I-80/Southbound I-680 Green Valley Road-Fairfield
3-Day Offramp and Onramp Closures
Start Friday, May 20 at 10:00 PM

SOLANO COUNTY – The California Department of Transportation (Caltrans) and its project partner the Solano Transportation Authority (STA) are nearing completion of the new Green Valley Road overcrossing above Interstate-80 (I-80) in Solano County.

As part of the work, starting Friday, May 20, crews will begin constructing the permanent roadway connection from the eastbound I-80 Green Valley Road off-ramp to the new Green Valley Road overcrossing.

EB I-80 Green Valley Road Offramp & Onramp-3-Day Closure
For worker and public safety, the Green Valley Road offramp from eastbound I-80, the onramp from Green Valley Road onto eastbound I-80 and southbound I-680 will be closed for three days. Closure starts Friday, May 20 at 10:00 PM until Monday, May 23 at 2:00 PM.

During the off-ramp closure, motorists traveling to Green Valley Road from eastbound I-80 are advised to exit eastbound I-80 at either the Red Top Road or Suisun Valley Road exits.

SEE LINK TO PROJECT WEBPAGE FOR DETAILED DETOUR MAPS:
http://www.dot.ca.gov/dist4/projects/solano8068012/

Eastbound I-80 Green Valley Road Offramp-3 Day Closure

• Detour-To Green Valley Road via Red Top Road
Motorists traveling to Green Valley Road via Red Top Road should exit eastbound I-80 at Red Top Road, then eastbound on Red Top Road, then northbound on Lopes Road, then continue on Lopes Road across the overcrossing until it becomes Green Valley Road.

• Detour-To Green Valley Road via Suisun Valley Road
Motorists traveling to Green Valley Road via Suisun Valley Road should exit eastbound I-80 at Suisun Valley Road, then westbound on Pittman Road, then northbound across the
I-80/Suisun Valley Road overcrossing, and westbound on Business Center Drive for about a 1/2 mile until reaching Green Valley Road.

Eastbound I-80/Southbound I-680 Green Valley Road Onramp-3-Day Closure
During the work, the Eastbound I-80 onramp and I-680 onramp from Green Valley Road will also be closed. Closure starts Friday, May 20 at 10:00 PM until Monday, May 23 at 2:00 PM.

• Detour-From Southbound Green Valley Road to Southbound I-680 Onramp
Motorists traveling from southbound Green Valley Road to southbound I-680 are advised to travel southbound on Green Valley Road, continue on southbound Lopes Road, then eastbound on Gold Hill Road and enter southbound I-680 from Gold Hill Road.

• Detour-From Northbound Green Valley Road to Southbound I-680 Onramp
Motorists traveling from northbound Green Valley Road to southbound I-680 are advised to make a U-turn at Business Center Drive, then southbound on Green Valley road, continue on southbound Lopes Road, then eastbound on Gold Hill Road and enter southbound I-680 from Gold Hill Road.

• Detour-From Southbound Green Valley Road to Eastbound I-80 onramp
Motorists traveling from southbound Green Valley road to eastbound I-80 are advised to travel southbound on Green Valley Road, then westbound on Red Top Road and enter eastbound I-80 from Red Top Road.


• Detour-From Northbound Green Valley Road to Eastbound I-80 onramp
Motorists traveling from northbound Green Valley Road to eastbound I-80 are advised to travel from Green Valley Road to eastbound Business Center Drive, southbound on Suisun Valley road, continued onto the overcrossing onto Pittman road, and enter eastbound I-80 from Pittman Road.


Motorists should expect delays and watch for detour signs and flaggers. The CHP will assist with traffic controls. All work is weather permitting.

Project Benefits
Once this stage of work is complete, motorists will be able to exit eastbound I-80 at Green Valley Road again, and for the first time travel northbound and southbound on the new Green Valley Road overcrossing above I-80. The new overcrossing will include new northbound and southbound traffic lanes, a new sidewalk, and a new bicycle lane.

Get additional project information: http://www.dot.ca.gov/dist4/projects/solano8068012/