Saturday, April 4, 2015

I-280 Rehab-Santa Clara County-Ramp Closures Start April 6

TRAFFIC ADVISORY UPDATE

Date: April 3, 2015
District Oakland
Contact: Bernard Walik
Phone: 510.286.5705

FOR IMMEDIATE RELEASE

Interstate 280 Rehabilitation Project Update
Schedule of Ramp Closures and Detours
From 4/06/15 to 4/12/15

(SANTA CLARA COUNTY)-The following ramps will be closed intermittently from Monday 4/06/15) to Sunday (4/12/15). Weekday construction is scheduled Monday through Thursday from 8:00 PM to 5:00 AM the following day. Weekend work will start Friday evening from 8:00 PM to 10:00 AM (Saturday morning) and Saturday evening from 8:00 PM to 10:00 AM (Sunday morning).

There will be various freeway and ramp closures during this project; however, Caltrans will always provide at least one open lane in either direction of travel and never close two consecutive ramps. The project is expected to be completed this summer 2015.

Ramp Closures and Detours for Monday 4/06/15 to Thursday 4/09/15:

NB I-280 / Wolfe Road on-ramp
Detour: From NB Wolfe Road to WB Homestead Road to SB De Anza Blvd to NB I-280
From SB Wolf Wolfe Road to WB Stevens Creek Blvd to NB De Anza Blvd to NB I-280

NB I-280 Wolfe Road off-ramp
Detour: Traffic to next off-ramp

NB I-280 / De Anza Blvd on-ramp
Detour: From NB De Anza Blvd that EB Homestead Road to SB N Wolfe Road to I-280
From SB N De Anza Blvd take on-ramp to SB I-280 to off-ramp to N Wolfe Road to I-280.

NB I-280 / DeAnza Blvd off-ramp
Detour: Traffic to next off-ramp


The following ramps will be closed on Friday (4/10/15) to Saturday (4/11/15):

NB I-280 / De Anza Blvd on-ramp
Detour: From NB De Anza Blvd that EB Homestead Road to SB N Wolfe Road to I-280
From SB N De Anza Blvd take on-ramp to SB I-280 to off-ramp to N Wolfe Road to I-280.

NB I-280 / DeAnza Blvd off-ramp
Detour: Traffic to next off-ramp

NB I-280 / NB SR-85 connector
Detour: From NB I-280 to Foothill Expressway to SB I-280 on-ramp to SB I-280 connector off-ramp to NB SR-85

NB I-280 / SB SR-85 connector
Detour: From NB I-280 take Foothill Expressway off-ramp to SB I-280 on-ramp to SB SR-85 off-ramp.

NB I-280 / Foothill off-ramp
Detour: Traffic to next off-ramp

NB I-280 / Foothill on-ramp
Detour: From NB Foothill Expressway to EB Homestead Rd to SB N. DeAnza Blvd to NB I-280 on-ramp. From SB Foothill Expressway on SB I-280 on-ramp to DeAnza Blvd off-ramp to NB I-280 on-ramp

The following ramps will be closed on Saturday (4/11/15) to Sunday (4/12/15):

NB I-280 / De Anza Blvd on-ramp
Detour: From NB De Anza Blvd that EB Homestead Road to SB N Wolfe Road to I-280
From SB N De Anza Blvd take on-ramp to SB I-280 to off-ramp to N Wolfe Road to I-280.

NB I-280 / DeAnza Blvd off-ramp
Detour: Traffic to next off-ramp

NB I-280 / NB SR-85 connector
Detour: From NB I-280 to Foothill Expressway to SB I-280 on-ramp to SB I-280 connector off-ramp to NB SR-85

NB I-280 / SB SR-85 connector
Detour: From NB I-280 take Foothill Expressway off-ramp to SB I-280 on-ramp to SB SR-85 off-ramp.

NB I-280 / Foothill on-ramp
Detour: From NB Foothill Expressway to EB Homestead Rd to SB N. DeAnza Blvd to NB I-280 on-ramp. From SB Foothill Expressway on SB I-280 on-ramp to DeAnza Blvd off-ramp to NB I-280 on-ramp

NB I-280 / Foothill off-ramp
Detour: Traffic to next off-ramp


NO WORK SATURDAY EVENING 4/04/15 TO SUNDAY 4/05/15 DUE TO EASTER

PLEASE NOTE: HERE ARE THE AREAS WHERE NOISE PRODUCING GRINDING OPERATIONS WILL TAKE PLACE:

Monday 4/06/15 to Wednesday 4/8/15
8:00 PM TO 5:00 AM Location of Grinding: NB 280 Tantau to DeAnza

Thursday 4/09/15
8:00 PM TO 5:00 AM Location of Grinding: NB I280 to Foothill

Friday 4/10/15 to Saturday 4/11/15
8:00 PM to 10:00 AM Location of Grinding: NB I-280 DeAnza Blvd to Foothill


Advance warning changeable message signs and detour signs are in place to assist motorists traveling in the area. For more information on this project please visit our website at: http://www.dot.ca.gov/dist4/280rehabilitationproject/

###