Interstate 280 Bridge Hinge Replacement Project 104-Hours (4 Days-8-Hours) Road Closure Planned for Memorial Day Holiday Weekend

Date:              May 15, 2014
District:         4 - Oakland
Contact:        Steven A. Williams              Allyn Amsk
Phone:          (510) 286-6195                     (510) 286-5445

FOR IMMEDIATE RELEASE

Interstate 280 Bridge Hinge Replacement Project
104-Hours (4 Days-8-Hours) Road Closure Planned for Memorial Day Holiday Weekend

San Francisco – In seven days the California Department of Transportation will close southbound Interstate 280 from downtown San Francisco to the Pennsylvania Avenue on-ramp. This closure is necessary in order to replace one bridge hinge on southbound I-280. Additional closures are planned for the Fourth of July and Labor Day holiday weekends to replace bridge hinges on northbound I-280.

The first closure is scheduled for the Memorial Day weekend. Southbound I-280 will be fully closed between downtown San Francisco and the Pennsylvania Avenue on-ramp.

Full southbound closure Begins: 9 p.m. Thursday evening, May 22
Full southbound closure Ends: 5 a.m., Tuesday morning, May 27.

Southbound on-ramp closures include:
  • Mariposa Street/18th Street on-ramp
  • 6th Street/Brannan on-ramp
  • King Street on-ramp

Detour: In general, southbound I- 280 traffic will detour to U.S. 101. Mariposa Street/ 18th Street traffic can also detour to the southbound I-280 Pennsylvania Avenue on-ramp.

Note: northbound I-280 will remain open over the Memorial Day Holiday Weekend.
                         
Additional closures are planned for
  • 4th of July Holiday Weekend (Thursday, July 3 – Tuesday, July 8)
  • Labor Day Holiday Weekend (Thursday, August 28 – September 2)

For more information about the project, visit the Department’s website at http://www.dot.ca.gov/dist4/projects/280Bridge, or follow us on Twitter @caltransd4.


# # #